Driving Through Time - The Digital Blue Ridge Parkway
Search Results:
- 1.
Building - razed
January 12, 1937 - 2.
Unsurfaced Road
February 2, 1937 - 3.
Drain Wall
February 2, 1937 - 4.
Car on Road
February 2, 1937 - 5.
Cumberland Knob Parking
February 2, 1937 - 6.
Completed Road
February 2, 1937 - 7.
Winding Road
February 2, 1937 - 8.
Cumberland Knob Drive
February 2, 1937 - 9.
Route 18 Crossing
February 2, 1937 - 10.
Route 18 Intersection
February 2, 1937 - 11.
Curved Road
February 2, 1937 - 12.
Finished Slopes
February 2, 1937 - 13.
Early construction
February 2, 1937 - 14.
Men cleaning gutter
February 2, 1937 - 15.
Intersection Corner
February 2, 1937 - 16.
Bridge Arch
February 3, 1937 - 17.
Bridge Abutment
February 4, 1937 - 18.
Rock embankment and stream
February 4, 1937 - 19.
Bridge #9 construction
February 4, 1937 - 20.
Rock embankment and culvert
February 4, 1937 - 21.
Bridge #8
February 4, 1937 - 22.
Bridge Construction
February 4, 1937 - 23.
Bridge Construction
February 4, 1937 - 24.
Construction materials
February 4, 1937 - 25.
Bridge at Site #7, Steel Construction
March 29, 1937 - 26.
North abutment and stringers
March 29, 1937 - 27.
East parapet wall south abutment
March 29, 1937 - 28.
Bridge at site #7, Steel stringers
March 29, 1937 - 29.
Bridge at site #7 Steel construction, looking back from south abutment
March 29, 1937 - 30.
Bridge at site #7 Steel construction
March 29, 1937 - 31.
Underside of bridge
April 6, 1937 - 32.
Riveters working
April 6, 1937 - 33.
Detail Pier #2
April 10, 1937 - 34.
Rail construction
April 10, 1937 - 35.
Unfinished road and bridge
April 10, 1937 - 36.
View of bridge #4
April 10, 1937 - 37.
View of road
April 10, 1937 - 38.
Detail of expansion dam
April 10, 1937 - 39.
Bridge #6
April 10, 1937 - 40.
Bridge Construction
April 10, 1937 - 41.
View of road
April 10, 1937 - 42.
Rail details
April 10, 1937 - 43.
Detail of expansion dam
April 10, 1937 - 44.
View of bridge
April 10, 1937 - 45.
Landscape North to Bridge #6
April 10, 1937 - 46.
Bridge #10 and Stream
April 12, 1937 - 47.
Bridge #8
April 12, 1937 - 48.
Left End of Bridge #9
April 12, 1937 - 49.
Bridge Rock Detail
April 12, 1937 - 50.
#9 Bridge, Down Stream, Cost $20,120
May 4, 1937 - 51.
Station 563 No 8 Bridge cost $34,053
May 4, 1937 - 52.
No.4 Arch Bridge, cost $12,000
May 4, 1937 - 53.
Looking back over bridge #5
May 4, 1937 - 54.
No. 5 Bridge, cost $17,520
May 4, 1937 - 55.
No. 5 Bridge, Cost $17,520, Pine Creek Bridge #5
May 4, 1937 - 56.
No.6 bridge, cost $15,139
May 4, 1937 - 57.
Guard rail, No.7 bridge
May 4, 1937 - 58.
Cumberland Knob Park Picnic Road
May 7, 1937 - 59.
Underside of Viaduct
May 18, 1937 - 60.
Bridge No. 3, 57' Span, Cost $19,462
May 18, 1937 - 61.
Bridge #4
May 18, 1937 - 62.
Bridge no. 9, cost $20,120 24' span
May 18, 1937 - 63.
Mailbox on parkway
May 18, 1937 - 64.
Bridge No.2 49'10" span, cost $11,894
May 18, 1937 - 65.
Bridge #7 approximate cost $45,000
May 18, 1937 - 66.
Bridge #7, guard rail and pier detail
May 18, 1937 - 67.
Bridge #5 42' span cost $17,520
May 18, 1937 - 68.
Bridge #7, approximate cost $45,000
May 18, 1937 - 69.
Completed Bridge #8
May 25, 1937 - 70.
Bridge #9
May 25, 1937 - 71.
Bridge #10
May 25, 1937 - 72.
Pine Creek Bridge #7
May 25, 1937 - 73.
Pine Creek Bridge #6
May 25, 1937 - 74.
Pine Creek Bridge #4
May 25, 1937 - 75.
Pine Creek Bridge #3
May 25, 1937 - 76.
Cars crossing Pine Creek Bridge #7
May 25, 1937 - 77.
Bridge #2
May 25, 1937 - 78.
Arch of Bridge #9
May 25, 1937 - 79.
Pine Creek Bridge #5
May 25, 1937 - 80.
Old state box culvert to be removed
June 1, 1937 - 81.
Parkway box culvert
June 1, 1937 - 82.
Saddle Mountain Valley. Lake site, looking up at valley, woods opposite
August 20, 1937 - 83.
Saddle Mountain Valley, Lake Site
August 20, 1937 - 84.
Unknown variety of plant 6 - 7' high, yellow flowers in bloom
August 20, 1937 - 85.
Saddle Mountain Valley, Lake Site from station 277
August 20, 1937 - 86.
Cumberland Knob Shelter Bldg #89
September 1937 - 87.
Fireplace in shelter on top of Cumberland Knob
October 1937 - 88.
Road through Cut
October 10, 1937 - 89.
Road and Bridge with Guard Stakes
October 10, 1937 - 90.
Cement stone gutter
October 10, 1937 - 91.
Rough Grade Road
October 10, 1937 - 92.
Rock Cut - Devil's Garden
October 13, 1937 - 93.
Back side of shelter
October 15, 1937
Refine Your Search
Types (1)
Photographs (93)Locations (14)
Section 2A (53) Milepost 225 (12) Milepost 224 (7) Cumberland Knob (3) Milepost 217 (3) Milepost 222 (3) Milepost 229 (3) Milepost 223 (2) Pine Creek Bridge #4 (2) Devil's Garden (1) See All ResultsSections (1)
2A (93)Counties (1)
Alleghany (93)